Russia
- Novaya Zemlya Loading Facility, Russia
-
-
SRK Consulting (Russia) Ltd commissioned CGR to prepare an outline cost estimate for a ship loading facility on the island of Novaya Zemlya off the north coats of Russia. The facility is required for loading 8,000 to 10,000 tonne vessels with fine and loose mined lead and zinc concentrates from a covered, heated stockpile facility.
- Cold Store Facility, Kamchatka, Russia
-
-
A cold storage facility was required to store fish (including pickled fish at -8oC) at Kamchatka on the Pacific Coast of Ukraine. Several options were investigated including a single storey bouilding and a two storey option. The required freezer capacity was 174,000m3 in one of the options.